Hinesville, Georgia

This project consists of the installation of over 10,000 feet of force main ranging in size from 8-15” including directional bores under roadways. The project also includes the demolition and replacement of the existing equipment at Stonehenge Pump Station.

  • Owner: City of Hinesville
  • Engineer: Simonton Engineering
  • Estimated Completion: August 2025

Continue reading

HMGMA Civil Works Package 2

HMGMA Civil Works
Package 2 Project

Hyundai Motor Group Metaplant America Civil Works Package 2

Ellabell, Georgia

The scope of work for the project included the installation of the gravity sewer system for the Hyundai Motor Group Metaplant America Project. This project also included the installation of two pre-built fiberglass pump stations as a part of the same sewer system.

  • Owner: Hyundai Motor Group
  • Engineer: Hyundai Engineering America
  • Estimated Completion: 2024