Skip to main content

Author: brittany

Pembroke Wastewater Treatment Plant

Pembroke
WWTP Project

Pembroke Wastewater Treatment Plant

Pembroke, Georgia

The scope of work for the project included: Construction of a new screen and grit structure; expansion of the water pollution control plant including an aeration basin, clarifier, digester, blowers, filters, UV disinfection system, and dewatering system; construction of a control building; and installation of associated electrical systems.

  • Owner: City of Pembroke
  • Engineer: M.E. Sack Engineering
  • Estimated Completion: 2027
  • Pembroke-main

  • Pembroke-2

  • Pembroke-WWTP

Continue reading

Folkston Wastewater Treatment Plant

Folkston
WWTP Project

Folkston Wastewater Treatment Plant

Folkston, Georgia

The scope of work for the project included: Grading, dredging, and cleaning of the reject pond; construction of concrete driveways; installation of drainage pipes and structures; selective demolition; installation of electrical controls; erosion control and grassing; installation of a manual filter screen; construction of an influent pump station; installation of an SBR system; installation of a disk filtration system; installation of UV disinfection; construction of a reject pump station; installation of a sludge dewatering system; installation of an emergency power supply; and installation of a transformer.

  • Owner: City of Folkston
  • Engineer: M.E. Sack Engineering
  • Estimated Completion: 2027
  • Folkston-Main

  • Folkston

  • Folkston-2

Continue reading

Mobis and OEM Metering Station

Mobis and OEM Metering
Station Project

Mobis and OEM Metering Station

Bryan County, Georgia

The scope of work for the project included: Construction of Metering Station Building including foundation, block, Hardie siding, trusses and roofing; installation of mechanical piping including propeller meters; yard piping; installation of HVAC; SCADA; and electrical.

  • Owner: Bryan County Board of Commissioners
  • Engineer: Thomas & Hutton
  • Estimated Completion: 2025

Continue reading

Lowcountry RWS – Elevated Storage Tank

Lowcountry RWS – Elevated
Storage Tank Project

Lowcountry RWS – Elevated Storage Tank

The scope of work for the project included: preliminary site work necessary for the construction of the water tank; installation of valve vault and valves; yard piping; installation of drain box and drain piping; grading; paving; and fencing.

  • Owner: Lowcountry Regional Water System
  • Engineer: Thomas & Hutton
  • Estimated Completion: 2026
  • lowcountry_rws_tank

  • lowcountry_rws_tank2

Continue reading

Battery JV Metering Station

Battery JV Metering
Station Project

Battery JV Metering Station

Bryan County, Georgia

The scope of work for the project included: Construction of Metering Station Building including foundation, block, Hardie siding, trusses and roofing; installation of mechanical piping including propeller meters; yard piping; installation of HVAC; SCADA; and electrical.

  • Owner: Bryan County Board of Commissioners
  • Engineer: Thomas & Hutton
  • Estimated Completion: 2025
  • battery_jv_ms2

  • battery_jv_ms

Continue reading

Wastewater Treatment Plant Upgrade – Division A

Wastewater Treatment Plant Upgrade
Division A

Wastewater Treatment Plant Upgrade – Division A

Wrightsville, Georgia

The Facility Upgrade Division A work shall be to increase the treatment capacity of the existing plant from a 0.7452 MGD Facility to a 1 MGD average monthly flow and a 3 MGD peak facility. The existing facility consists of an Aeration Pond, a Facultative Pond and a Polishing Pond. These existing ponds are proposed to remain. A new plant site is proposed approximately 900’ southeast of the existing plant headworks.

  • Owner: City of Wrightsville
  • Engineer: Ingram & Associates, LLC.
  • Estimated Completion: TBD
  • wrightsville_wwtp3

  • wrightsville_wwtp2

  • wrightsville_wwtp

Continue reading

WWTP Update and Improvements

WWTP Update and
Improvements

WWTP Update and Improvements

Folkston, Georgia

The work to be performed consists of furnishing all labor, materials, and equipment to complete the WWTP Update and Improvements. More specifically, the project will consist of clearing and grubbing, grading, dredging and cleaning of existing lagoon, granite roadway base, rock drive, asphalt paving, gravity sewer, drainage pipe and structures, electrical controls, erosion control and grassing, complete influent pump station, complete headworks, complete inline pump station, complete SBR system, complete disk filtration system, complete UV disinfection, complete reclaimed water pump station, complete sludge dewatering system, emergency power supply, transformer, and laboratory casework.

  • Owner: City of Folkston
  • Engineer: M.E. Sack Engineering
  • Estimated Completion: August 2026

Continue reading

Green Zone Well and Transmission Main

Green Zone Well and Trasmission
Main Project

Green Zone Well and Transmission Main

Hinesville, Georgia

The work to be performed consists of furnishing all labor and materials to complete the Green Zone Well and Transmission Main Project. More specifically, the project will consist of the installation of a large diameter Upper Floridan Well, well house, mechanical piping facilities, electrical and standby power plus 10,000 LF of 18” water transmission main.

  • Owner: City of Hinesville
  • Engineer: Simonton Engineering
  • Estimated Completion: August 2025
  • DJI_0891_web

  • DJI_0887_web

Continue reading

Lift Station 21 & 22 Upgrades

Lift Station 21 & 22
Upgrades

Lift Station 21 & 22 Upgrades

Pooler, Georgia

The work will include wet well cleaning, regrouting and recoating; pump removal and replacement; removal of below ground valve pits and placement above ground; electrical upgrades; bypassing of the station during construction; generator installation; and site grading and drainage.

  • Owner: City of Pooler
  • Engineer: Pittman Engineering Co., LLC
  • Estimated Completion: April 2026

Continue reading

Hinesville Sewer System Upgrades

Hinesville Sewer
System Upgrades

Hinesville Sewer System Upgrades

Hinesville, Georgia

This project consists of the installation of over 10,000 feet of force main ranging in size from 8-15” including directional bores under roadways. The project also includes the demolition and replacement of the existing equipment at Stonehenge Pump Station.

  • Owner: City of Hinesville
  • Engineer: Simonton Engineering
  • Estimated Completion: August 2025

Continue reading